The connection method between the hydraulic hammer and the excavator

2026-01-07 Maintenance Add to favorites
(1) Connect the "P" port of the flow divider to the pump's oil out

(1) Connect the "P" port of the flow divider to the pump's oil outlet with a hose.  

(2) Connect the "A" port of the flow divider to the control valve's oil inlet with a hose.  

(3) Connect the "H" port of the flow divider to the hydraulic hammer's oil inlet pipeline.  

(4) Connect the "T" port of the flow divider to the oil tank.  

(5) Connect the hydraulic hammer's return oil pipe to the excavator's main return oil pipeline.  

(6) The pipe diameter for each connection port should be: when the host's oil supply is less than 70L/min, the pipe diameter should be ø16mm; when the host's oil supply is greater than or equal to 70L/min, the pipe diameter should be ø20mm.